PROJECT CONTROL TOWER · AI ENABLED

AI Material Control Dashboard

Procurement, logistics, inventory intelligence and cost status as of 15 August 2026
Total MRSMR
120

+12 this month 96% coded

PO CommitmentPO
$76.4M

62% of budget 86 POs

On-Site ProgressOS
53%

+4.8% vs last cutoff 17 packages

Delivery Attention!
18

6 critical required ≤ 30d 5 vendors

Paid to DatePV
$36.9M

48% of commitment 27 invoices open

OVERALL PROGRESS

Plan vs Actual S-Curve

Planned 86%Actual 72%−14.0%
0%25%50%75%100%Cut-off 15 AugMarAprMayJunJulAugSep

PROCUREMENT HEALTH

Package Pipeline

120Packages

On track 78

Watch 24

At risk 12

Critical 6

MRS18
PO22
MFG31
SHIP19
SITE30

COST CONTROL

Budget vs Commitment

BudgetCommitment
Mechanical
$0.0M
Piping
$41.7M
Electrical
$0.0M
Instrument
$0.0M
Civil
$34.7M
HVAC
$0.0M

ACTION REQUIRED

Delivery Attention List

Package / MaterialStatusRequiredProgress
PKG-0026.6kV Switchgear PanelCritical09-0711d overdue
84%
PKG-003Control Valve AssemblyCritical09-2015d overdue
54%
PKG-006Instrument CableReady to Ship10-2924d left
74%
PKG-010Fire Fighting PumpReady to Ship12-2027d left
71%
PKG-013HVAC Air Handling UnitIn Transit01-2830d left
88%
PKG-014Power TransformerManufacturing02-1033d left
58%
PKG-017Cooling Water PumpIn Transit03-2136d left
85%